VILL’UP WORKS START AGAIN !

Construction on Vill’Up, the destination for shopping and fun, resumes, with a planned opening in autumn of 2016!

After the fire that took place on the Vill’Up construction site last August, dredging and decontamination work have since finished. Vill’Up had been just weeks away from opening when the fire occurred. Organised with the Cité des Sciences et de l’Industrie, reconstruction work will focus on the metallic carpentry (characteristic of the building); weatherproofing and exterior; construction of a new fire-resistant partition between the third bay of the Cité des Sciences et de l’Industrie and Vill’Up; the refurbishing of all technical networks; and the reconstruction of areas of the Pathé cinema affected by the fire.